Who we are
Anchored in Switzerland and internationally active, WALO is managed as a family business in the 4th and 5th generation. For over 100 years, WALO has focused on the combination of consistency and innovation.
What we do
WALO is active as an innovative total solutions company in all markets of the construction industry. The family-owned company has established itself as a reliable partner in the construction industry and infrastructure projects in Switzerland and worldwide with its decades of experience and the permanent development of sustainable as well as economical solutions.
Projects
We have successfully implemented many challenging projects. Therefore, we proudly let our references speak for our work.
Products
Whether residential, industrial, healthcare, outdoor or for sports and leisure facilities - seamless floor coverings have to meet a wide variety of requirements on a permanent basis.
Career
Good buildings and thus satisfied customers require precise construction work. All our employees, from unskilled workers to engineers, play a key role in ensuring that we achieve this goal time and time again.
Locations
With our locations in three countries, we are successfully active for you worldwide.
Between October 2019 and March 2020, we renewed the tracks slab track at Zurich Airport in a consortium. A four-week total closure was available for each track of 600 m each. The supply of the construction site could only be carried out at night and by rail, as there were no normal accesses via the airport. The new track was constructed with Vossloh DFF 304 system and cast-in-place concrete supports (25% UHFB UB and 75% SCC C50/60).
Concrete production presented a major challenge. Due to limited accessibility, it was not economical to deliver fresh concrete directly from the plant. The solution was to produce both the UHFB and the SCC concrete in the tunnel using a compulsory mixer. The next challenge was the on-site concrete transport. Since the platform was already occupied by the parallel project on the one hand, and on the other hand the payload of only 500 kg/m2 was not suitable for the concrete logistics, and in addition the quantities were too small for pumping, we developed a track-going e-trolley with which we could drive over the fine-tuned track.
The island construction site with very limited access possibilities and practically no installation areas as well as the tight time and space conditions required demanding logistics. At the same time, the platform lighting was replaced in a parallel project. Furthermore, the immediate proximity to the public had to be taken into account and the health and safety measures for underground work had to be implemented.
We appreciate your interest in the WALO Group and are happy to answer any questions you may have.