• Who we are
  • What we do
  • Projects
  • Products
  • Career
  • Contact
  • Who we are
  • What we do
  • Projects
  • Products
  • Career
  • Contact
Back

Who we are

Anchored in Switzerland and internationally active, WALO is managed as a family business in the 4th and 5th generation. For over 100 years, WALO has focused on the combination of consistency and innovation.


Overview
Back

What we do

WALO is active as an innovative total solutions company in all markets of the construction industry. The family-owned company has established itself as a reliable partner in the construction industry and infrastructure projects in Switzerland and worldwide with its decades of experience and the permanent development of sustainable as well as economical solutions.


Overview
Back

Projects

We have successfully implemented many challenging projects. Therefore, we proudly let our references speak for our work.


Overview
Back

Products

Whether residential, industrial, healthcare, outdoor or for sports and leisure facilities - seamless floor coverings have to meet a wide variety of requirements on a permanent basis.


Overview
Back

Career

Good buildings and thus satisfied customers require precise construction work. All our employees, from unskilled workers to engineers, play a key role in ensuring that we achieve this goal time and time again.


Overview

N04/06 Galgenbuck tunnel

The Galgenbuck Tunnel in the canton of Schaffhausen has a total length of 1,138m. After about two and a half years of driving, the breakthrough took place in February 2016.

Project description

The Galgenbuck Tunnel in the canton of Schaffhausen has a total length of 1,138m. After about two and a half years of driving, the breakthrough took place in February 2016.
Once again, precision work and pinpoint preparation were required. The position of the main heading as well as the two small counter heading tunnels was systematically checked and the accuracy of the breakthrough was in the centimeter range.

 

Special features

Since the start of the tunnelling work in July 2013, an average of two to three blasts were carried out per day. A total of around 120,000m3 of rock material was excavated and around 1,700t of steel and 26,000m3 of concrete were used in the tunnel. However, the tunnel breakthrough and the end of the blasting and construction work are only a further stage. On the last 125m to the portal Bahntal in the area of the counter heading tunnels, the widening of the entire tunnel cross section was carried out.

WALO_Untertagbau_Galgenbucktunnel5
WALO_Untertagbau_Galgenbucktunnel3
WALO_Untertagbau_Galgenbucktunnel2
WALO_Untertagbau_Galgenbucktunnel1
Contact

Walo Bertschinger AG
Giessenstrasse 5
8953 Dietikon 1

Location
Galgenbucktunnel, Schaffhausen
Service

Underground Construction