• Who we are
  • What we do
  • Projects
  • Products
  • Career
  • Contact
  • Who we are
  • What we do
  • Projects
  • Products
  • Career
  • Contact
Back

Who we are

Anchored in Switzerland and internationally active, WALO is managed as a family business in the 4th and 5th generation. For over 100 years, WALO has focused on the combination of consistency and innovation.


Overview
Back

What we do

WALO is active as an innovative total solutions company in all markets of the construction industry. The family-owned company has established itself as a reliable partner in the construction industry and infrastructure projects in Switzerland and worldwide with its decades of experience and the permanent development of sustainable as well as economical solutions.


Overview
Back

Projects

We have successfully implemented many challenging projects. Therefore, we proudly let our references speak for our work.


Overview
Back

Products

Whether residential, industrial, healthcare, outdoor or for sports and leisure facilities - seamless floor coverings have to meet a wide variety of requirements on a permanent basis.


Overview
Back

Career

Good buildings and thus satisfied customers require precise construction work. All our employees, from unskilled workers to engineers, play a key role in ensuring that we achieve this goal time and time again.


Overview

EP Küssnacht well section 4

Repairs to the carriageway and all engineering structures will ensure the availability and safety of the national highway for another 15 years.

Project description

The section of the N04 was built between 1976 and 1981 and was in need of rehabilitation. The maintenance project included repair work on the carriageway and on all engineering structures such as bridges, underpasses and retaining walls.

As part of the maintenance measures, the N04 between the Schwyz junction and the north portal of the Mositunnel was upgraded to such an extent that only minimal maintenance measures will be necessary until the complete renewal of the route. The availability and safety of the national road was thus guaranteed for another 15 years.

The following work was carried out in the various construction phases:

In Phase 0 (preliminary work, July - December 2019), the temporary access roads and installation sites were constructed. Scaffolding was erected at the bridge soffits and repair work started. At the same time, the bridge bearings were replaced.

In Phase 1 (Altdorf lane, January - March 2020), anchor work started on the uphill retaining walls. In the road area, various cable conduit blocks and foundations for signal gantries were newly constructed. At the retaining walls Urmi 02 and Zingel, the existing bracket heads were demolished and provided with a new guide wall. The Sechzehni bridge was repaired on one side.

In phase 2 (Altdorf lane, March - July 2020), repair, waterproofing and mastic asphalt work followed on all viaducts. On the uphill retaining walls, the concrete longarines to the anchors were constructed. On the Zingelbrücke exit ramp, the bracket heads were rebuilt under traffic.
Furthermore, in this phase the deck pavements were replaced in stages and provided with temporary markings. The noise barrier "Mitte" was replaced.

In the last phase 3 (Zurich lane, July - November 2020), the Schwyz exit was completely closed for 5 weeks. During this time, the decks on both the Zingel and Urmiberg bridges were demolished, various repair works were carried out and the waterproofing was renewed. On the Zingel bridge, 250 m of bracket head were also demolished and rebuilt. At the end of the total closure, the surface courses from the Urmiberg bridge to the Schwyz junction were renewed.

In addition to the work in the area of the Schwyz exit, repair, sealing and mastic asphalt work was carried out on the Sechzehni and Muota bridges and the Brunnen cantonal road underpass. In night work, the surface courses were renewed in the Mositunnel and Brunnen exit areas. Finally, the surface courses in the route were renewed and the final marking was applied.

Special features

The major challenge of the project was the very short construction time for the rehabilitation of the total 1.35 km long viaducts and overpasses. Therefore, the construction sequence was optimized down to the last detail.

A special highlight was the five-week intensive construction phase in July and August 2020, when approx. 6,500 m2 of bridge superstructure including the Schwyz exit ramp were renewed during the summer vacations.

WALO_Betonsanierung_EP Küssnacht-Brunnen Abschnitt 4 Bild 1
WALO_Betonsanierung_EP Küssnacht-Brunnen Abschnitt 4 Bild 2
WALO_Betonsanierung_EP Küssnacht-Brunnen Abschnitt 4 Bild 3
WALO_Betonsanierung_EP Küssnacht-Brunnen Abschnitt 4 Bild 4
WALO_Betonsanierung_EP Küssnacht-Brunnen Abschnitt 4 Bild 5
Contact

Walo Bertschinger AG
Giessenstrasse 5
8953 Dietikon 1

Location
Küssnacht, SZ
Service

Concrete Rehabilitation and Hydrodynamics

Civil Engineering

Mastic Asphalt

Laboratory

Construction sum
CHF 50 Mio. 
Builder
Federal Roads Office FEDRO
Brühlstrasse 3
4800 Zofingen
Construction management
F. Preisig AG
Hagenholzstrasse 83b
8050 Zürich
Company
ARGE Urschwyz
Walo Bertschinger AG
Marti Bauunternehmung AG
Anliker AG Bauunternehmung
Share page
placeholder_hero_3

Contact us

We appreciate your interest in the WALO Group and are happy to answer any questions you may have.

© 2024 Walo Bertschinger. All rights reserved.